Ontario Excavation Safety: Slopes, Shoring & the 1.2-Metre Rule (O. Reg. 213/91)

TL;DR: In Ontario, a support system — sloping, shoring, or a trench box — is required wherever a worker may enter an excavation 1.2 m (4 ft) or deeper (O. Reg. 213/91 s. 234(2)(a)). Slope Type 1 and 2 soil at 1:1 (45°) to within 1.2 m of the bottom, Type 3 at 1:1 (45°) from the bottom, and Type 4 at 1:3 (18.4°) from the bottom (s. 234(2)(e)(f)(g)). A trench deeper than 6 m (20 ft) or wider than 3.6 m needs an engineered support system designed by a professional engineer (s. 235(2)). Over 2.4 m (8 ft), a 1.1 m barrier is required at the top of any non-sloped wall (s. 233(4)).

The rules below come from Ontario Regulation 213/91 (Construction Projects) under the Occupational Health and Safety Act, Part III — Excavations, sections 222 through 242. They apply every time a shovel or backhoe breaks ground on an Ontario construction project where a worker may enter the excavation. Numbers here are verified against the O. Reg. 213/91 Part III text; confirm the current consolidation at ontario.ca/laws before relying on it.

Why is 1.2 metres the trigger?

A cubic metre of soil weighs roughly 1,100 to 1,800 kg depending on type and moisture. At 1.2 metres (4 ft) deep, a wall collapse buries a worker from the waist down under more weight than a small car — enough to crush the pelvis, legs and internal organs in seconds, and to suffocate as the chest can no longer expand. You cannot dig someone out by hand in time. Below 1.2 m a worker can usually climb out unassisted; above it they cannot, which is why the regulation sets the line there. According to O. Reg. 213/91 s. 234(2)(a), a support system is required whenever a worker may enter an excavation 1.2 m (4 ft) or deeper. The trigger turns on the phrase "a worker may enter" — a machine-dug utility trench nobody enters does not need a support system, but you must still keep the edge clear (s. 233(1)) and, over 2.4 m, guard against falls (s. 233(4)).

What are the four soil types and their slope angles?

O. Reg. 213/91 s. 226 sets out four soil types, and s. 234(2) sets the maximum slope for each. Type 1 is hard, very dense soil with no water seepage that only comes out with machinery — hardpan, consolidated clay, some glacial tills. Type 2 is very stiff, dense soil that a pick enters with moderate effort — silty clay, less-dense tills. Type 1 and Type 2 walls may be sloped to within 1.2 m (4 ft) of the bottom at a gradient of 1:1 (45°) — one metre of cut-back for every metre of height — with the bottom 1.2 m left vertical (s. 234(2)(e)). Type 3 is stiff-to-firm or compact-to-loose soil, or any previously-excavated (backfilled) soil, showing surface cracking and seepage; it must be sloped 1:1 (45°) from the bottom — no vertical portion (s. 234(2)(f)). Type 4 is soft, very loose, wet soil that runs or flows and exerts fluid pressure — muskeg, quicksand, saturated silty clay; it must be sloped 1:3 (18.4°) from the bottom, three metres of cut-back for every metre of height (s. 234(2)(g)). A 3 m deep cut in Type 4 needs 9 m of cut-back on each side, which is why Type 4 almost always means a support system instead of open-cut sloping. Soil can change within one trench — firm clay giving way to a pocket of sand or an old backfilled service run — so where more than one type is present, s. 227(3) requires you to classify to the highest (weakest) number present.

Sloping, shoring, or a trench box — which one?

Section 234 gives three ways to protect a worker in an excavation. Sloping (or benching) cuts the walls back to the soil's required gradient — the simplest method, but the hungriest for space. A 2 m deep cut in Type 3 (1:1) needs 2 m of cut-back on each side; on a residential lot with 1.5 m of side-yard, that is impossible. Shoring actively holds the walls back: timber shoring uses sheathing, wales and struts (the prescribed member sizes live in the Table to s. 238, good to 6 m depth); hydraulic shoring uses aluminum or steel rams that pre-load the walls and can be installed from the top without anyone entering the trench. Every prefabricated, hydraulic or engineered support system must be designed by a professional engineer, with the drawings kept on site (s. 236). A trench box (trench shield) does not hold the walls back — it protects whoever is inside it if the wall lets go. It must be rated for the depth and soil, and workers are only protected while inside the box. The support system must extend at least 0.3 m (about 12 in) above the top of the excavation (s. 241(1)), and a ladder for access and egress must sit within the protected area (s. 240).

When does an excavation need a professional engineer?

Under O. Reg. 213/91 s. 235(2), a trench deeper than 6 m (about 20 ft) or wider than 3.6 m must use an engineered support system designed for the specific location and project. At that depth the lateral earth pressure outruns off-the-shelf shoring and trench-box ratings, and a miscalculation moves thousands of kilograms of soil in seconds. The engineer's signed and sealed drawings must specify the system type, member sizes and spacing, installation sequence, maximum depth and the soil conditions assumed — and they must be on site while the system is in place (s. 236(7)). Installing the system in a way that departs from those drawings is an OHSA offence (s. 236(2)); a variation has to be approved in writing by an engineer (s. 236(5)). Separately, where an excavation may affect an adjacent building or structure, a professional engineer must specify the required precautions in writing (s. 229). Note that shafts and tunnels are not Part III excavations at all — they fall under Part IV (Tunnels, Shafts, Caissons and Cofferdams, ss. 243-331), which adds a Notice of Project, ventilation, atmospheric monitoring and rescue requirements.

How often must an excavation be inspected?

O. Reg. 213/91 does not set a fixed general inspection interval — a point often misstated. What it does say: no worker may enter an excavation that does not comply with Part III (s. 224), and where a support system relies on a professional engineer's written opinion, the engineer or a competent worker must inspect it as often as that opinion specifies (s. 234(3), (5)). In practice, IHSA guidance — and good sense — is to have a competent worker inspect before each shift and after any event that changes the ground: rainfall, freeze-thaw, blasting or traffic vibration, or a surcharge load placed at the edge. Rain saturates clay, adds weight and strips cohesion, turning a stable Type 2 wall into a Type 4 failure surface within hours; frozen soil looks solid but sloughs off in blocks as it thaws. Monday morning after a wet weekend is the classic danger window. The competent worker checks every wall face for tension cracks, bulging and seepage, confirms the support system is undamaged, and keeps the 1 m (3 ft 3 in) edge clear zone (s. 233(1)) and equipment back from the wall (s. 233(3)).

Underground utilities: call before you dig

O. Reg. 213/91 s. 228 requires all gas, electrical and other services in and near the dig to be located and marked before excavation begins, and any service that may pose a hazard to be shut off and disconnected. In Ontario that means contacting Ontario One Call (1-800-400-2255 or ontarioonecall.ca) before you dig; the utility owners then mark the approximate centre line of their buried plant with paint or flags. IHSA treats locate accuracy as 1 m either side of the mark, so hand-dig within 1 m of any marked utility — no machine in the hand-dig zone — and support exposed pipes and cables so they cannot fail (s. 228(3)). The stakes are absolute: a punctured high-pressure gas main fills a trench with an explosive atmosphere in seconds, distribution-voltage electrical contact (14.4 kV to 44 kV across much of Ontario) is instantly fatal, and a broken watermain can flood a trench fast enough to drown a worker. If marks are missing, faded or disturbed, stop and call for a re-locate — it costs nothing.

Running crews across multiple Ontario jobs? ToolFluency's Ontario contractor toolkit and crew management app keep your timesheets, job tracking and site paperwork in one place. Pair this checker with the Fall Protection Checker and the rest of the WSIB & OHSA safety tools.

About Excavation Safety Checker

O. Reg. 213/91 s. 234 requires a support system — sloping, shoring or a trench box — wherever a worker may enter an excavation 1.2 m (4 ft) or deeper (s. 234(2)(a)); below 1.2 m a support system is not required unless a hazard exists.

By the ToolFluency team · Updated September 2026

Free Ontario excavation safety checker. Enter depth, soil type, and site conditions to determine sloping angles, shoring needs, trench box requirements, and inspection checklists under O. Reg. 213/91 ss. 222-242. Key thresholds: 1.2m (4 ft) trigger, 2.4m, 6m (engineer required).

How to use

  1. Pick the excavation type — trench (depth greater than width), open excavation, shaft or tunnel. Shafts and tunnels are governed by Part IV (ss. 243-331), not the Part III excavation rules.
  2. Enter the planned depth in metres or feet. A support system (sloping, shoring or a trench box) is required wherever a worker may enter an excavation 1.2 m (4 ft) or deeper — O. Reg. 213/91 s. 234(2)(a).
  3. Choose the soil type (1-4) per s. 226. The tool returns the required slope gradient: Type 1 and 2 = 1:1 (45°, bottom 1.2 m may stay vertical), Type 3 = 1:1 (45°), Type 4 = 1:3 (18.4°) — s. 234(2)(e)(f)(g).
  4. Tick the site hazards — water present, adjacent buildings, buried utilities, heavy equipment near the edge, public traffic. Each adds a control: keep the excavation free of water (s. 230), engineer-specified precautions near structures (s. 229), locate services before digging (s. 228), keep machines back from the edge (s. 233(3)), or a 1.1 m fall barrier and traffic control (s. 233(4)).
  5. Print the checklist. A competent worker should inspect before each shift and after any event that affects stability (rain, freeze-thaw, vibration, a surcharge load at the edge); where a support system relies on a professional engineer's written opinion, inspect as often as the opinion specifies (s. 234(3), (5)).

Examples

1.5 m trench, Type 3 soil, water table near grade
Trench at 1.5 m in Type 3 (previously-excavated / soft) soil with water present. Verdict: support system required (s. 234). Slope Type 3 at 1:1 (45°) from the bottom — about 1.5 m of cut-back on each side (s. 234(2)(f)) — or use a trench box. Keep the excavation reasonably free of water (s. 230); soil that runs or flows when saturated is Type 4 (1:3, 18.4°). Keep the 1 m edge clear zone (s. 233(1)).
4 m basement excavation, Type 2 firm soil
Open excavation at 4 m in Type 2. Slope 1:1 (45°); the bottom 1.2 m may stay vertical, so cut back about 2.8 m of the 4 m height on each side (s. 234(2)(e)). Because it is over 2.4 m deep, a barrier at least 1.1 m high is required at the top of any non-sloped wall (s. 233(4)). An adjacent foundation 2 m from the edge needs engineer-specified precautions (s. 229); any prefabricated/hydraulic/engineered support is PE-designed (s. 236). Keep equipment back from the edge (s. 233(3)).

Frequently asked questions

When is a protective system required in an Ontario excavation?

O. Reg. 213/91 s. 234 requires a support system — sloping, shoring or a trench box — wherever a worker may enter an excavation 1.2 m (4 ft) or deeper (s. 234(2)(a)); below 1.2 m a support system is not required unless a hazard exists. Slope gradients depend on soil class: Type 1 and 2 are sloped to within 1.2 m of the bottom at 1:1 (45°), Type 3 at 1:1 (45°) from the bottom, and Type 4 at 1:3 (18.4°) — s. 234(2)(e)(f)(g). Any prefabricated, hydraulic or engineered support system must be designed by a professional engineer (s. 236), and the support system must extend at least 0.3 m above the top of the excavation (s. 241(1)).

What are the four soil types and their slope gradients in Ontario?

Section 226 of O. Reg. 213/91 classifies soil as Type 1 (hard, very dense, no water seepage — excavated only by machine), Type 2 (very stiff, dense, damp when excavated), Type 3 (stiff-firm to compact-loose, or previously-excavated, with surface cracking and seepage) or Type 4 (soft, very loose, wet, sensitive, exerts fluid pressure). The maximum-slope gradients are set by s. 234(2): Type 1 and Type 2, 1:1 (45°) sloped to within 1.2 m of the bottom; Type 3, 1:1 (45°) from the bottom; Type 4, 1:3 (18.4°) from the bottom. Where more than one type is present, classify to the highest number (s. 227(3)). Backfilled or previously-excavated soil is Type 3, or Type 4 if it is wet or saturated.

Who inspects an excavation in Ontario and how often?

O. Reg. 213/91 does not fix a general inspection interval. No worker may enter an excavation that does not comply with Part III (s. 224), and where a support system relies on a professional engineer's written opinion the engineer or a competent worker inspects as often as the opinion specifies (s. 234(3), (5)). In practice, IHSA guidance is to inspect before each shift and after any event that affects stability — rainfall, freeze-thaw, vibration or a surcharge load at the edge. Inspection records should be kept on site for the Ministry inspector.

When must a professional engineer design the support system?

O. Reg. 213/91 s. 236 requires a professional engineer to design every prefabricated, hydraulic or engineered support system, with signed and sealed drawings kept on site. Under s. 235(2), a trench deeper than 6 m or wider than 3.6 m must use an engineered support system designed for the specific project. Timber shoring may instead follow the prescribed member sizes in the Table to s. 238 for depths up to 6 m. A professional engineer must also specify in writing the precautions where an excavation may affect an adjacent structure (s. 229). Installing a system in a way that departs from the drawings is an OHSA offence (s. 236(2)).

Is a Notice of Project required for a trench?

For a trench more than 1.2 m deep that a worker may enter, the constructor must give the Ministry of Labour, Immigration, Training and Skills Development (MLITSD) notice before work begins (s. 6 and s. 7 of O. Reg. 213/91). A full Notice of Project (Form 1000, or the online e-NOP) is required where the project meets the s. 6(1) thresholds — for example a trench over 1.2 m deep and over 30 m long, total cost over $50,000, or any work required to be engineer-designed. The notice lists the constructor, project address, type of work and dates, and is one of the first documents an inspector asks to see.

What edge protection and setback rules apply to an excavation?

Section 233(1) requires a level area at least 1 m from the upper edge of each wall to be kept clear of equipment, excavated soil, rock and material. No vehicle or machine may be positioned where it could affect wall stability (s. 233(3)). Where a person could fall into an excavation more than 2.4 m deep, a barrier at least 1.1 m high is required at the top of any wall not sloped to the s. 234(2) gradient (s. 233(4)). A roadside excavation also needs OTM Book 7 traffic control — signs, barrels and barriers.

What's the difference between a trench and an excavation in the regulation?

O. Reg. 213/91 defines an excavation as the hole left in the ground after removing material, and a trench as an excavation where the depth exceeds the width (s. 1). The narrow, parallel-walled geometry of a trench produces the classic simultaneous cave-in, so trenches carry the stricter engineered-support trigger at 6 m depth or 3.6 m width (s. 235(2)). Shafts (axis steeper than 45° from horizontal) and tunnels are not Part III excavations at all — they fall under Part IV (ss. 243-331), which adds Notice, ventilation, atmospheric-monitoring and rescue requirements.

Part of ToolFluency’s library of free online tools for WSIB & OHSA. No account needed, no data leaves your device.

Embed this tool on your site (free)
Paste this where you want the tool. Please keep the attribution link.
<iframe id="tf-excavation-safety" src="https://toolfluency.com/tools-v2/wsib-ohsa/excavation-safety.html?embed=1" width="100%" height="640" loading="lazy" style="border:1px solid #e2e2e2;border-radius:12px;max-width:760px" title="Excavation Safety Checker by ToolFluency"></iframe>
<script>addEventListener("message",function(e){var f=document.getElementById("tf-excavation-safety");if(f&&e.source===f.contentWindow&&e.data&&e.data.tfEmbedHeight){f.height=e.data.tfEmbedHeight}});</script>
<p>Powered by <a href="https://toolfluency.com/tools-v2/wsib-ohsa/excavation-safety.html">Excavation Safety Checker</a> — free tools by ToolFluency</p>